What is the site installation process of your company's steel structure plant?

In recent years, steel structure workshop is popular in China, because its materials are processed and manufactured in the factory, and then transported to the site for installation, which not only ensures the quality, but also ensures the speed. Dalian Guangtong Steel Structure Co., Ltd. for the steel structure plant site installation process is as follows:

1. Hoisting of main structure

Ground splicing of steel beams, erection of steel columns, hoisting of steel beams, connection of secondary structures, correction of main structure deviation, installation of crane beams, hoisting of mezzanine, fire retardant coating.

Main control quality: the deviation of main structure shall meet the specification and design requirements, and the initial and final tightening of high-strength bolts shall meet the requirements.

2. Secondary structure installation

Roof wall purlin, roof wall support, flange support and other structural installation.

3. Installation of roof panel and insulation layer

The insulation layer shall be laid first, and then the roof panel shall be installed.

Main control quality: the roof is mainly waterproof, so it is necessary to overlap the Kanban with the board, nail the situation, glue to be applied fully, glue to be applied should be wiped clean, the coating on the board surface should not be damaged to prevent rust, etc.

4. Wall maintenance and installation

Mainly is the wall insulation layer and wall panel installation.

Main control quality: the wall is mainly a beautiful problem, and a window waterproof problem, and also installation deviation problem. So the bottom should be flat, the whole plane should be flat, and the flatness deviation between plates should meet the requirements.

5. Detailed structure

It mainly includes the installation of some trimming, such as the corner between the roof and the wall, the corner of the wall, the flashing between the wall panel and the brick wall, the door and window trimming, etc.

Main control quality: the detailed structure is the last link, and also one of the main aesthetic items, so horizontal and vertical is the most basic.

Dalian Guangtong Steel Structure Co., Ltd. is an enterprise specialized in the design and manufacture of steel structure and non-standard metal parts. The company covers an area of 18000 square meters, including 13000 square meters of plant area. Guangtong steel structure currently produces steel structure columns, beams, bridge formworks, steel structure billboards, shelves, workshops, workshops, etc. Our company has always advocated "safety first, quality first and green production", put product quality first, strictly control the quality of raw materials and products before leaving the factory, and take quality service as the core to meet all the needs of customers.